OVERVIEW:

In cooperation with Lend Lease, JBS&G Consultant’s and Pure Contracting, EMS removed 25,000 tonnes of contaminated material to a certified landfill.

Under EMS ASB2 supervision, 25,000 tonnes of asbestos contaminated general solid waste was transported and disposed. EMS provided a holistic service, which made it possible to provide the highest industry standard at a competitive rate.

EMS exceeded the clients’ expectations, and finished the project in less than 3.5 weeks, 10 days earlier than expected.

For further details on this project, please contact EMS on 02 9834 2998.

PROJECT:

Cartage and Dispose of Asbestos contaminated Stockpiles

CLIENT:

Lend Lease Pty Ltd

PROJECT LOCATION:

Barangaroo Central, Millers Point, NSW